Set progress
rillsoft_task_progress_setSet a single task's actual progress (0-100%) by hand; the value is passed to predecessors and successors.
Instructions
Sets the actual progress of a task (0 to 100 %). It sets one task by hand; deriving the progress of every task from the status date goes through rillsoft_task_progress_recalculate, and the planning data of the task itself through rillsoft_task_update. The value is passed along to predecessors and successors. One undo step.
Input Schema
| Name | Required | Description | Default |
|---|---|---|---|
| uuid | Yes | UUID of the task | |
| progressPercent | Yes | actual progress in percent (0 to 100) |
Output Schema
| Name | Required | Description | Default |
|---|---|---|---|
| wbs | Yes | WBS code | |
| name | Yes | name | |
| uuid | Yes | UUID of the element | |
| start | Yes | start, DD.MM.YYYY hh:mm | |
| finish | Yes | finish, DD.MM.YYYY hh:mm | |
| number | Yes | number of the element; unique even for split tasks | |
| effortHours | Yes | effort in hours | |
| effortDoneHours | Yes | completed effort in hours | |
| progressPercent | Yes | actual progress in percent |