rillsoft_task_progress_recalculateRecalculate actual task progress from the current status date for all tasks, writing progress values without changing dates; use for deriving completion status from RP-computed progress.
Instructions
Derives the actual progress of every task from the current status date, computed by RP. It writes progress, not dates - moving unfinished work goes through rillsoft_project_status_date_reschedule, and a single task by hand through rillsoft_task_progress_set. One undo step.
Tool call template
This tool declares no required parameters. Add optional parameters from the input schema as needed.
{
"id": 1,
"jsonrpc": "2.0",
"method": "tools/call",
"params": {
"arguments": {},
"name": "rillsoft_task_progress_recalculate"
}
}Input Schema
| Name | Required | Description | Default |
|---|---|---|---|
No arguments | |||
Output Schema
| Name | Required | Description | Default |
|---|---|---|---|
| statusDate | Yes | status date of the project, DD.MM.YYYY hh:mm |