Move a whole project to a new start date, the way Microsoft Project's Move Project does. Every task without actual work moves by the difference between the old and the new project start, counted in working days on the project's working calendar, so durations, links and lags stay as they are and no date lands on a non-working day. Tasks with an actual start, any progress, or status Done stay where they are, as do tasks whose dates come from Microsoft Planner; tasks linked after them are rescheduled from their links. Dated constraints move with their task. Deadlines move only with moveDeadlines: true. The project start becomes start, and the project end (the target finish, project.endDate.to in the result) moves by the same working days, so this is also the tool that moves a plan's finish. The finish the plan actually reaches is finish.to: the latest task finish the project schedule computes after the move (finish.from before it). Tasks that stay can finish later than every task that moves; then finish.to is later than project.endDate.to, finish.held gives how many such tasks and the latest (drivingTaskId, drivingTaskTitle), and finishNote states it in one sentence. update_project's endDate changes only the target date and moves no task. dryRun: true returns the same counts (moving, staying and why, deadlinesMoving, constraintsMoving) and the finish, and writes nothing. Requires the project-level project.edit permission. A start equal to the current one returns changed: false and writes nothing. The result carries undo, the move that puts the plan back. With fromTaskId and workingDays instead of start, only part of the plan moves: every task whose start is after the day fromTaskId finishes moves by workingDays working days on the project calendar (negative is earlier), and tasks that start on or before that day, including tasks running alongside it, stay. The named task stays too unless includeFromTask: true (for a summary task, every task under it). Started, Done and Planner-dated tasks in that range stay and are counted in staying, as in a whole move. The project start and project end do not change; finish reports the finish the plan reaches. A moved task linked after a task that does not move gets a Start No Earlier Than at its new start so it keeps it (shift.pinned counts them). The result's shift names the task and the day the scope starts after, and undo is the same shift back. Refused with a message when this workspace does not have it turned on. With finishBy (YYYY-MM-DD) instead of start, the tool finds the start itself: it moves the plan by whole working days on the project calendar so the finish the schedule computes lands on or before finishBy, the latest such start its previews find, and the result's finishBy gives the asked day, whether the finish reaches it (reached), the start chosen, the shift in working days (workingDays) and how many previews it ran. A finishBy move sets the target finish (project.endDate.to) to finishBy itself, not the old target moved by the same working days, and targetNote states the new and the old target in one line; its undo puts the old target back. When work already started drives the finish, no start reaches an earlier day and finishExplain says why. Where finishBy is turned on, the result also carries weekdays: the start, the finish and the asked day, each with its weekday name. finishBy is refused with a message where it is not turned on.