p6_project_summary
Get a one-call overview of a Primavera P6 project, including key dates, activity and relationship counts, critical-path totals, percent complete, baseline variance, and schedule state.
Instructions
One-call overview of a project (values of the last F9): project (name, calendar), dates (data date, planned start, must finish by, scheduled finish, last schedule run, first start and last finish of the activities, scheduled finish minus must finish by in calendar days and in working days of the project calendar (None when it is unreadable)), activities (by status, by type, open, open milestones), relationships (successor in the project; from and to other projects), critical (counts of open activities, LOE and WBS summary left out, as p6_critical_path), percent_complete (primary = units: actual / at completion units, labor plus nonlabor, P6 Units % Complete as p6_list_wbs; p6_progress_curve gives % of the budget instead; physical: physical % weighted by budget units; duration; activities completed; units_vs_physical_mismatch: activities with units whose physical % and units % differ by more than 0.01 point), baseline (the project baseline, baselines attached, the one used: baseline= else the project baseline, its scheduled finish and data date; every key present, null without a baseline; finish variance = scheduled finish minus the baseline's scheduled finish in calendar days and in working days of the project calendar, baseline planned units % at the data date and spi_units = earned units / baseline planned units, earned value and linear spread as p6_progress_curve), counts (WBS, assignments, resources, calendars, code assignments) and schedule_state.
Tool call template
Replace each placeholder with a value matching the input schema. Only required parameters are included; add optional parameters as needed.
{
"id": 1,
"jsonrpc": "2.0",
"method": "tools/call",
"params": {
"arguments": {
"project": "<project>"
},
"name": "p6_project_summary"
}
}Input Schema
| Name | Required | Description | Default |
|---|---|---|---|
| project | Yes | Project ID as shown in P6 (p6_list_projects). | |
| baseline | No |