"source": "sf.gov DBI — Recheck plans, Resubmit for streamlined housing, Affordable housing online",
"source_urls": [
"https://www.sf.gov/recheck-plans-OTC-building-permit-application/",
"https://www.sf.gov/resubmit-building-permit-new-housing-using-citys-streamlined-process/",
"https://www.sf.gov/apply-building-permit-affordable/"
],
"last_verified": "2026-02-17",
"description": "Post-filing processes: plan rechecks, streamlined housing resubmission, affordable housing online permits",
"plan_recheck": {
"when": "At the end of plan review, you may need to revise plans and bring them back for a recheck",
"process": {
"step_1": "Revise plans and print updated sheets",
"step_2": "Contact assigned plan checker via email to coordinate timing",
"step_3": "Register at Permit Center via Qless system"
},
"otc_recheck": {
"registration": "Register as 'OTC recheck'",
"queue": "Two customers queue per plan checker; may wait onsite",
"contact": "Email plan checker for availability"
},
"inhouse_recheck": {
"registration": "Register as 'In-house recheck' with scheduled appointment",
"stations": "Reviews at stations 68 and 69",
"contact": "Schedule formal appointment with plan checker"
},
"qless_times": {
"morning": "8 AM start (9 AM Wednesdays)",
"afternoon": "11:30 AM start"
},
"location": "Permit Center, 49 South Van Ness, 2nd floor",
"hours": "Mon-Fri 8-5 (Mon 9-5). Queues close 4:30 PM; payments until 5 PM.",
"staff_directory_note": "If you lack plan checker contact info, find it in the DBI staff directory",
"contact": "dbicustomerservice@sfgov.org"
},
"streamlined_housing_resubmission": {
"description": "Withdraw and resubmit housing permits filed before 1/1/2024 to benefit from faster timelines and enhanced legal protections",
"eligibility": {
"filed_before": "January 1, 2024",
"project_type": "At least two-thirds residential"
},
"steps": [
"Withdraw original application using Unissued Extension or Withdrawal Form",
"Request partial refund of permit fees via Refund Request Form",
"Review step-by-step guide for In-house Review submission",
"Resubmit through online permit application portal"
],
"legal_context": {
"AB_2234_2022": {
"completeness_notice": "Building departments must notify within 15 days if application is complete",
"approval_timelines": {
"25_units_or_fewer": "30 business days",
"26_plus_units": "60 business days"
}
},
"AB_1114_2023": {
"effect": "Broadens post-entitlement permit definition; removes ability to subject permits to public appeals or legal challenges",
"benefit": "Insulates applicants from costly post-issuance legal battles"
}
}
},
"affordable_housing_online": {
"qualifying_projects": [
"100% affordable housing projects",
"Development Agreement projects (require Board of Supervisors + Mayor approval)"
],
"submission_requirements": {
"plans": "Editable PDFs, max 350 MB each",
"title_blocks": "Project address, sheet count, sheet names required",
"stamps": "Every sheet must have signature and stamp",
"back_check_page": "Include city's required Back Check Page PDF for Bluebeam submissions"
},
"priority_confirmation": "Request letter from City department partner if project qualifies",
"contact": "dbi.epr@sfgov.org"
}
}