baseline_variance
Identify schedule slips by comparing each activity's start, finish, and duration against a baseline, ranked by worst finish variance, with project finish variance totals.
Instructions
Start / finish / duration variance of every activity against a baseline, in working days (positive = later than baseline), worst finish variance first, plus the project finish variance. Baseline source, in order: baseline_path (a baseline schedule file, matched on activity ID), the baseline stored in the file (MS Project Baseline 0), or P6 Planned Start/Finish (labelled as such, since it is not a true baseline).
Input Schema
| Name | Required | Description | Default |
|---|---|---|---|
| path | Yes | ||
| limit | No | ||
| project | No | ||
| baseline_path | No | ||
| baseline_project | No |