A test suite or a job pipeline takes as long as it takes — unless some of it can run side by side. parallelmap takes the workload graph — every job's name, its duration, and the names of the jobs that must finish before it starts — and maps out what can safely parallelize:

  • Levels — the jobs grouped by depth. Level 0 holds the jobs with no dependencies; every other job sits at one level above its deepest dependency. Everything in a level can run together, once the levels below it are done.

  • Sequential vs parallel time — the sum of all durations against the makespan with unbounded workers (the largest earliest finish), and the speedup between them. All reported seconds are rounded to 3 decimals, and the speedup is computed from those rounded values.

  • Critical path — the chain that sets the parallel time, in execution order. Ties — for the finishing job and for each step back along the chain — go to the smallest job name, so the path is fully deterministic.

  • Worker schedule — pass a worker count and a greedy list schedule assigns the jobs in (level, name) priority order, each to the worker that frees up first (lowest index on a tie), starting no earlier than its dependencies' finishes under that schedule. The schedule reports each job's worker, start, and finish, sorted by (start, worker, job), plus the resulting makespan. Without a worker count there is no schedule and the makespan is the unbounded parallel time.

  • Cycle detection — when the jobs cannot be scheduled at all, parallelmap does not error out or guess. It reports ok: false with the exact cycle: a depth-first search over names and dependencies in ascending order returns the first cycle it finds as the list of jobs forming it (a job that depends on itself reports as a one-name cycle), with the time fields null.

The graph must be closed: a depends_on entry naming a job that was not supplied is a validation error, as are a missing or duplicate job name, a missing, negative, or non-finite duration, and a worker count that is not an integer of at least 1. Errors name the offending path (for example jobs[1].depends_on[0] references unknown job "build") and no partial map is produced. The computation is pure and local: no network, no configuration, no files read beyond the input you pass in.

CLI

npx @reneturcios/parallelmap map --input args.json
npx @reneturcios/parallelmap --version

args.json contains the full arguments object:

{
  "jobs": [
    { "name": "compile", "duration_seconds": 30 },
    { "name": "unit", "duration_seconds": 45, "depends_on": ["compile"] },
    { "name": "lint", "duration_seconds": 10, "depends_on": ["compile"] },
    { "name": "package", "duration_seconds": 5, "depends_on": ["unit", "lint"] }
  ],
  "workers": 2
}

depends_on defaults to [] per job and workers is optional overall. The map is printed as JSON:

{
  "ok": true,
  "levels": [["compile"], ["lint", "unit"], ["package"]],
  "sequential_seconds": 90,
  "parallel_seconds": 80,
  "speedup": 1.125,
  "critical_path": ["compile", "unit", "package"],
  "cycle": [],
  "schedule": [
    { "job": "compile", "worker": 0, "start": 0, "finish": 30 },
    { "job": "unit", "worker": 0, "start": 30, "finish": 75 },
    { "job": "lint", "worker": 1, "start": 30, "finish": 40 },
    { "job": "package", "worker": 1, "start": 75, "finish": 80 }
  ],
  "makespan_seconds": 80
}

Exit codes: 0 on success, 1 on a runtime error (including an unreadable or invalid input file, or invalid input), 2 on a usage error.

Related MCP server: genpark-topological-sorter-tarjan-scc-skill

MCP server

npx -y @reneturcios/parallelmap mcp

MCP client config:

{
  "mcpServers": {
    "parallelmap": {
      "command": "npx",
      "args": ["-y", "@reneturcios/parallelmap", "mcp"]
    }
  }
}

Tools

  • map_parallelization — Map which jobs or tests can safely run in parallel.

    • jobs (array, required, at least one) — jobs as {name, duration_seconds, depends_on?} objects; name is unique across the set and each depends_on entry names another supplied job

    • workers (integer, optional, at least 1) — when given, a greedy schedule onto that many workers is included

    Returns {ok, levels, sequential_seconds, parallel_seconds, speedup, critical_path, cycle, schedule, makespan_seconds} — or, on a cycle, {ok: false, cycle, levels: [], sequential_seconds, parallel_seconds: null, speedup: null, critical_path: [], schedule: [], makespan_seconds: null}.

Docker

docker run -i ghcr.io/cloudcorprecords/parallelmap
docker run --rm -v "$PWD:/w" ghcr.io/cloudcorprecords/parallelmap map --input /w/args.json

Development

npm install
npm run build   # tsc -> dist/
npm test        # tsx --test test/*.test.ts (pure local, no network)
npm run dev     # run the CLI from source

License

MIT — Copyright (c) 2026 Rene Turcios

Tool Schema Changelog

Recent tool additions, removals, and schema changes observed during successful MCP inspections.

Loading tool schema changelog…

    Related MCP Connectors

    Related MCP Servers

    • A
      license
      Not graded
      quality
      B
      maintenance
      Enables deterministic dependency reasoning over declared graphs, allowing users and AI agents to validate acyclicity, resolve targets, identify runnable parallel layers, assess impact, and explain blockers.
      Apache 2.0
    • A
      license
      Not graded
      quality
      B
      maintenance
      Enables MCP clients to run zero-dependency graph algorithms—including topological sorting, strongly connected component detection, shortest paths, maximum flow, minimum spanning trees, and PageRank—for agent dependency resolution and execution planning.
      7
      MIT
    • A
      license
      Not graded
      quality
      Not graded
      maintenance
      Enables agents to resolve dependencies and analyze directed graphs through topological sorting, strongly connected components, shortest paths, maximum flow, minimum spanning trees, and centrality ranking via MCP.
      MIT
    • A
      license
      B
      quality
      C
      maintenance
      Enables running planned batches of shell commands in parallel locally or over SSH, with dependency ordering, timeouts, cancellation, and per-task result collection.
      4
      MIT