EV Charger Installation Planner
ev_charger_install_costWork out the circuit a home EV charger needs, panel triage, utility install cost references and federal credit rules. Returns safety first, the exact 125% minimum breaker calculation, panel triage, unpriced extras and dated federal 30C rules. Reference cards are utility and DOE program figures, not a price for this home. A licensed electrician and permit are needed; confirm local requirements and inspection. Pure rules and Decimal, no network, model or clock. Web and MCP share the free daily allowance.
Input Schema
| Name | Required | Description | Default |
|---|---|---|---|
| level | No | Charging level; omit when unknown. | |
| extras | No | ||
| run_feet | No | Estimated routed panel-to-charger length, not straight-line distance. | |
| panel_amps | No | Panel/service rating, echoed only; a panel label alone cannot decide an upgrade or price the job. | |
| spare_space | No | Compatible breaker space for a new circuit. | |
| charger_amps | No | Rated or installer-set maximum charging current in amps. | |
| installed_on | No | Placed-in-service date YYYY-MM-DD; omitted follows the after-2026-06-30 rule. | |
| capacity_check | No | Electrician load calculation result; not_done means not assessed. | |
| existing_circuit | No | Suitable dedicated circuit already at the parking spot. |