get_schedule_risk
Read the Monte Carlo schedule risk runs of a project. Returns the newest run (status QUEUED, RUNNING, DONE or FAILED) and, when that run is not finished, the newest finished run. A finished run carries a summary: the P50, P80 and P90 finish dates, the plan date (the latest stored task finish, as the Gantt shows it) and its chance of being met, the finish as the links schedule it, the target date and its chance when one was set, and how many risk events were sampled. includeResult=true adds the whole stored result of the finished run (finish histogram and curve, milestone dates, task criticality and duration sensitivity). runId reads one run by id instead. Read-only; runs are started from the project Risks tab or the REST API.
Input Schema
| Name | Required | Description | Default |
|---|---|---|---|
| runId | No | Optional. One run of this project by id, in place of the newest. | |
| projectId | Yes | ||
| includeResult | No | Default false. Adds the whole stored result of the finished run. |